Voters approve Building Generations Bond for school construction and improvement!!!!

Davis School District is thrilled voters chose to invest in its students with the passage of the bond on Election Day. While the $475 million bond will not increase the tax rate, the district understands the responsibility placed upon it by taxpayers. These projects will have a positive impact on the educational experience for generations to come.

Bountiful Elementary School Principal Kristin McDonough... "Our students, faculty and staff, and community are so excited to have a new building with plenty of space for students to learn and grow. We would like to carry the great spirit and pride of Bountiful Elementary into a new building, and we look forward to the opportunity to expand our arts and academic programs with an updated facility."

Rebuilding Sunset Jr. and Bountiful Elementary, as well as building a new jr. high school in West Point are the top priorities for Davis School District.

  • Sunset Jr. Rebuild
    • Plans completed in January 2023
    • It will be bid after board approval in March 2023
    • Construction begins after board approval in March 2023
    • Projected completion date 2025

      Hogan & Associates: Construction Manager/General Contractor on both jr. high projects. They were approved by the board on September 6.
       
  • Bountiful Elm. Rebuild
    • Design begins Jan 4
    • Bids in Fall of 2023
    • Complete for Fall of 2025
       
  • New Jr High located at SE corner of 700 S 4500 W, West Point
    • Plans are expected to be completed in December 2022
    • Bid in January 2023
    • Construction begins after board approval in February 2023
    • Projected completion date Fall 2025
       
  • Remodel/expansion/upgrade projects:
    • Bountiful High: Fall 2025
    • Clearfield High: Fall 2025
    • Layton High: Fall 2026
    • Kaysville Jr.: Fall 2026
    • Burton Elementary: Fall 2026
    • Vae View Elementary: Fall 2027
    • Clinton Elementary: Fall 2024* Timeline determined by UDOT widening 1800 N. and subject to change
       
  • Other Projects: Completed by Fall 2028
    • AC projects in auditoriums and gyms
    • Construction of school tracks/turf fields at three jr. high schools
    • Other projects include kitchens, windows, energy upgrades, playground equipment, restrooms, and tracks
    • Land for future school sites